THE OGUZ – GABALA - BAKU WATER PIPELINE PROJECT IN AZERBAIJAN
 
Baku-Oguz-Gabala water pipeline opening speech by Azerbaijan President İlham Aliyev: Baku City Water began to reach.

Atinak has undertaken the design and construction part of the 251 km long water pipeline project. GRP pipes, made up of DN 2000 mm, run from Oguz to Baku thru Gabala. The owner of the project is the AZERSU Joint Stock Company. The project began in 2007 and is ongoing.

Client:
Turan Hazinedaroglu Construction Co.- Tekser Construction Co.- Gence Korpu Tikinti Joint Venture (The main contractor)

Services Provided:
▪ The installation of 251 km of DN 2000 mm and 5 km of DN 1400 mm GRP pipes and fittings, bedding and backfilling workmanship,
▪ Checking the production quality of GRP pipes and fittings,
▪ Orientation and checking the excavation of trenches with the employer's heavy construction equipment,
▪ Hydraulic testing of joints
▪ Installation of valves and accessories in wash out and air relief chambers

 

 

 

 