VIDEO |
 |
|
QUALITY POLICY |
 |
|
CONTACT US |
 |
|
|
THE OGUZ – GABALA - BAKU WATER PIPELINE PROJECT IN
AZERBAIJAN
|
|
Baku-Oguz-Gabala water pipeline opening speech
by Azerbaijan President İlham Aliyev: Baku City
Water began to reach.
Atinak has
undertaken the design and construction part of the 251
km long water pipeline project. GRP pipes, made up of DN
2000 mm, run from Oguz to Baku thru Gabala. The owner of
the project is the AZERSU Joint Stock Company. The
project began in 2007 and is ongoing.
Client:
Turan Hazinedaroglu Construction Co.- Tekser
Construction Co.- Gence Korpu Tikinti Joint Venture (The
main contractor) |
Services Provided:
▪ The installation of 251 km of DN 2000 mm and 5 km of
DN 1400 mm GRP pipes and fittings, bedding and
backfilling workmanship,
▪ Checking the production quality of GRP pipes and
fittings,
▪ Orientation and checking the excavation of trenches
with the employer's heavy construction equipment,
▪ Hydraulic testing of joints
▪ Installation of valves and accessories in wash out and
air relief chambers
|