Aim of the project is to supply Kilis with water until 2020. Pumping stations, 15.364 kms of pipeline, tanks and chlorination facilities are included in this project.

Owner:
State Water Works / Turkey (DSI)

Technical Specs. of the Construction:
▪ GRP and PE100 pipes between DN350-600 mm.
▪ Total length of pipes constructed is 15.364 m
▪ 2 Depot of 500 m3 each,
▪ 2 Pumping stations, one of which has 3 boosters with frequency convertors, whereas the other one has a fixed speed booster.

Agreement Info:
▪ Bidding Date: 27.09.2004
▪ Tender Value: 3,257 Million US$
▪ Starting Date: 15.03.2005
▪ Completion date: 11.11.2005
 

 

 

 